Landed House Construction Cost Calculator Singapore.

Create a transparent preliminary budget for a terrace, semi-detached or detached house using your selected project assumptions.

Read the guide

A single cost-per-square-foot figure rarely represents the complete budget for a landed house. This calculator separates the core building estimate from demolition, site allowances, specialist items, contingency, professional fees and GST.

You choose the construction rate: YuHuang does not present one generic PSF amount as suitable for every house. Use a rate supported by current project information, comparable scope or professional advice.

Free planning tool

Build an indicative landed-house budget

Enter amounts excluding GST. Review every assumption before using or sharing the result.

What the calculator includes

The core estimate is the entered construction floor area multiplied by the selected construction rate. Separately entered works are then added before percentage allowances are calculated. The tool keeps these components visible so a reader can challenge or replace each assumption.

What a PSF rate must define

  • Whether the area is GFA, construction floor area or another measurement basis
  • Terrace, semi-detached or detached house type
  • New build, reconstruction or additions and alterations
  • Structural system, façade, finishes and M&E standard
  • Pricing date and expected tender or construction period
  • Main-contractor preliminaries, overhead and profit
  • Basement, lift, swimming pool and specialist exclusions
  • Demolition, ground conditions, restricted access and external works

Costs commonly outside a headline construction rate

Depending on the rate source, exclusions may include land, financing, temporary accommodation, loose furniture, professional fees, authority charges, utility connections, demolition, site remediation, boundary works, specialist equipment and GST. Obtain a written inclusions-and-exclusions schedule before comparing rates.

From preliminary budget to cost plan

An early area-and-rate estimate is useful for feasibility. As the design develops, replace broad allowances with measured quantities, elemental cost plans, supplier information and project-specific risk allowances. Update the pricing date and record every revision.

For broader cost references, review YuHuang's construction unit-rate schedule and pre-tender estimating guide.

GST assumption

The calculator defaults to Singapore's prevailing 9% GST rate. GST applies according to the supplier, supply and transaction circumstances; confirm which amounts are taxable and whether quoted prices are inclusive or exclusive of GST. See the current IRAS GST rate.

Reference and share this calculator

Architects, property professionals and homeowners may link to this transparent budgeting tool. Suggested reference: YuHuang Estimating, Landed House Construction Cost Calculator Singapore.

Need a landed-house budget based on your drawings?

Send the proposed floor areas, drawings, specifications, site information and programme. YuHuang can prepare a measured, project-specific cost plan.