Construction Claims Consultant · Singapore

Construction claims,read the way thetribunal will read them.

Claims advisory delivered by a partner of Yuhuang Estimating — a Chartered Quantity Surveyor who is also a qualified Arbitrator, with 33 years on Singapore’s largest building and civil contracts, including the Deep Tunnel Sewerage System and LTA rail. We build, and defend, EOT, loss & expense and variation claims under the SIA form and PSSCOC.

⏱ Claims run on deadlines. The earlier we see your contract, the more we can protect.
SIA Conditions of ContractPSSCOCSecurity of Payment ActSOP AdjudicationArbitrationExtension of TimeLoss & ExpenseProlongation Cost
SIA Conditions of ContractPSSCOCSecurity of Payment ActSOP AdjudicationArbitrationExtension of TimeLoss & ExpenseProlongation Cost
Two sides of every dispute

Which side are you on?

Because our partner has sat as arbitrator, we can credibly act for either party — the detail that loses one side’s claim is the detail that defends the other. Choose your path.

AClaimant

I’m making a claim

Main contractors & sub-contractors. The EOT was refused, LDs loom, a variation won’t be valued, or your payment claim was slashed and the SOP clock is running.

  • Extension of time refused or under-granted
  • Prolongation & loss-and-expense written off
  • Variation stuck at the schedule of rates
  • Payment slashed — SOP adjudication deadline live
See how we build your claim
BRespondent

I’m defending a claim

Developers, owners, architects, consultants, SOs. A large EOT and loss-and-expense claim has landed, or an adjudication is lodged — and the board wants to know what’s actually real.

  • Independent assessment of an inflated claim
  • Protect your LD entitlement against an EOT
  • Rebut global & unsubstantiated quantum
  • A defensible figure for final account or tribunal
See how we defend your position

A lawyer argues the words. A quantity surveyor prices the loss. The rare advisor does both — and reads your claim already seeing how an arbitrator will decide it.

The lawyer

Argues the words

Strong on entitlement and law — but cannot build the quantum, the delay analysis, or the cost that proves the number.

The ordinary QS

Prices the loss

Can measure and value — but doesn’t think like the tribunal that will decide whether the claim stands.

Chartered QS + Arbitrator

Does both

Builds the claim that makes the lawyer’s job easy — and often unnecessary — because it’s already written to survive a tribunal.

Scope of advisory

Seven things we resolve

Post-award contract and claims advisory — for the contractor making the claim, and the owner, architect or consultant defending it.

01

Loss & Expense

Recovering — or testing — the additional cost of delay and disruption, not limited to prolongation.

ClaimDefence
02

Delay & Extension of Time

Entitlement, notices, and the delay analysis a tribunal will actually accept.

ClaimDefence
03

Valuation of Variations

Fair valuation when the contract rates no longer fit the changed work — beyond the schedule of rates.

ClaimDefence
04

Contract Interpretation

Rules of interpretation and order of precedence — which document prevails, and what the words mean.

Either
05

SOP Act Adjudication

Payment claims, payment responses and adjudication applications — on the statutory clock.

ClaimDefence
06

Arbitration Support

Quantum and delay analysis built to stand as evidence, alongside your solicitors.

ClaimDefence

Our Contracts & Claims partner

A Chartered Quantity Surveyor & qualified Arbitrator — in partnership with Yuhuang Estimating

Our claims advisory is led by a partner of Yuhuang Estimating: a Chartered Quantity Surveyor who is also a qualified Arbitrator, with 33 years on major building and civil contracts — including the Deep Tunnel Sewerage System (DTSS) and LTA rail. Fluent in the SIA Conditions, PSSCOC and the Security of Payment Act.

Chartered QSQualified Arbitrator33 yrs PQESIA & PSSCOC
The proof

Earned on the projects that set the standard.

0
Years post-qualification practice
DTSS
Deep Tunnel Sewerage System, civil
LTA
Major rail civil contracts
SIA + PSSCOC
Building & civil contract forms
How it works

From “do I even have a claim?” to a clear position — in 48 hours

Send your contract

WhatsApp or email your contract and key correspondence. Strictly confidential; NDA on request, and it reaches the principal — not a general inbox.

Get a position view

Within 48 hours: is the claim — or the defence — real? What is it worth? And what is at risk on the clock right now?

Pursue it, or defend it

A quoted scope only if you decide to proceed. Assessment first, engagement second — you spend nothing to learn where you stand.

Built to be the answer

The questions buyers — and AI search — actually ask

Each answer is written to be quoted: a direct definition first, the detail beneath.

What’s the difference between EOT and loss & expense?

Extension of time is about time — relief from liquidated damages. Loss & expense is about money — the additional cost of the delay. They are assessed under different clauses, on different tests, and one does not follow automatically from the other.

A contractor can win the EOT and still recover nothing in prolongation if it cannot prove actual loss caused by a compensable event. Winning the time does not win the money.

Do I need a claims consultant or a lawyer?

Often the consultant first. Most claims are won or lost on the QS work — the records, the entitlement, the quantum — long before a lawyer is needed.

We build the claim that makes the lawyer’s job easy, and frequently unnecessary. When arbitration is required, we work alongside your solicitors and reduce what you spend on them.

How disputes are resolvedSOP AdjudicationArbitrationLitigation
SpeedFast (statutory)Months–yearsYears
CostLowHighHigh
FinalityInterim — “pay now, argue later”Final & bindingFinal & binding
ConfidentialYesYesNo (public)
Best forCash-flow / progress paymentComplex final disputes
Before you ask

Straight answers

What will this cost? I’m already losing money. +

The first step is free and fixed-scope — a confidential position view, no engagement, no obligation. A single under-valued variation or a missed prolongation head can dwarf any advisory fee. Beyond the first look, fees are staged and quoted before you commit.

Is this confidential? +

Every enquiry is treated in strict confidence. Nothing you send is shared, and we will work under NDA from first contact. Your message reaches the principal directly.

You also do estimating — isn’t that a conflict? +

It’s exactly why our numbers are credible: we price live tenders every day, so we know how rates are really built up. We run a conflict check before accepting any matter and decline where there’s any clash. Your matter is never touched by anyone connected to the other side.

It might be too late — has a deadline passed? +

Maybe not — and that is precisely why to send the contract now. Many notice provisions are conditions precedent, but whether a deadline truly bars your claim depends on the exact wording and the facts. We’ll tell you where you stand quickly, before assuming the worst.

Find out if your claim is real — in 48 hours.

WhatsApp or email your contract and key correspondence. A Chartered QS and qualified Arbitrator will tell you whether your claim, or your defence, holds — what it’s worth, and what’s at risk on the clock.

Confidential · No obligation · Reviewed by a Chartered QS & qualified Arbitrator, Yuhuang Estimating’s claims partner · NDA on request